Tekmar Group has completed its role in the Dogger Bank A offshore wind farm by supplying essential cable protection systems (CPS) for the project’s inter-array cables.

This month, Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, achieved a significant milestone with the installation of all inter-array cables at the site.

Over 328 kilometres of 66 kV inter-array cables, manufactured by Hellenic Cables, were laid by DEME Offshore’s Viking Neptun, with burial works being completed by the company’s Living Stone Vessel.

This network of 95 cables, some stretching up to 8.6 miles, links Dogger Bank A’s 95 Haliade-X 13 MW turbines to the offshore converter station. From there, electricity is converted to direct current and transmitted to the onshore converter station via an advanced HVDC system.

The successful installation followed extensive underwater surveys to secure a clear cable-laying corridor, said Tekmar.

Source: offshoreWIND.biz (https://www.offshorewind.biz/2024/07/30/tekmars-cable-protection-systems-for-dogger-bank-a-delivered/?%3Futm_source=offshorewind&utm_medium=email&utm_campaign=newsletter_2024-07-31)