Norway’s government has unveiled measures to accelerate the development of renewable power and electricity networks, including simplified assessment requirements and a two-year deadline for processing grid applications.
The government said it wants to halve the average time needed to develop national and regional grids compared with before it took office in 2021.
Energy Minister Terje Aasland added that the measures are expected to have their full effect towards the end of the current parliamentary term and into the 2030s, while also delivering results in the short term.
The measures include removing the right of state administrators and other state authorities to raise objections to grid infrastructure, while maintaining the Sámi Parliament’s right to object.
The government will also ask Statnett and the Norwegian Water Resources and Energy Directorate to prioritise progress on the most important projects for the power system.
For onshore wind, the government plans to simplify municipal processes by removing the requirement for a zoning plan and enshrining municipalities’ right to approve or reject projects in separate legislation outside the Planning and Building Act.
Municipalities will also receive wind power revenues earlier, with the state to advance revenues from the production tax from the start of construction, with details to follow in the 2027 state budget.
“Wind power should be developed with municipalities, not against them. Municipalities’ right to say yes or no to wind power will remain, but we want to make the processes simpler, less contentious and more transparent to the wider public,” said Aasland.
“Sámi interests and considerations relating to nature and the environment are central parts of the current licensing process, and will continue to be so.”
Source: reNews